September 20 → October 15 2021

Concrete Trails, The Post Building, Irrigation, and Basketball Courts

The Post Building continues now that the center structure is up.  Walls are taking shape.  Concrete trails are being poured around the site, along with irrigation laterals and heads.  The basketball courts subsurface has been installed, with concrete going in the week of the Sept. 20th.  Playground drainage is installed in preparation for equipment and safety surfacing.