January 07 → January 14 2022

Three Week Look Ahead Description

Concrete pouring has been ongoing - contractor estimates that only three major pours are left - one of which is the heated concrete at The Peak Sledding Hill shelter.  Infields of the Revolution Pump Track are almost finished.  Site furnishings being installed where flatwork is finished.  Ongoing electrical work at The Post Building.  The pump house building on the corner of Powers Street and Erie Parkway will soon begin to take shape, starting with the foundation and floor slab, followed by installation of the three-water source pump.